Tuesday, March 15, 2011

Montana Bridge girder installation

> As part of the widening of the Montana Bridge, the contractor will install the girders to build the roadway. This activity requires the full closure of the intersection of Montana Av between Church Ln and Sepulveda Bl. Sepulveda Bl will be maintained with one lane of traffic in each direction. Closure of the Montana off ramp will be necessary. Installation is anticipated to take place on the night of Wednesday, March 16, 2011. Anticipated work and closure hours are from 9PM to 6AM, weather permitting. Please see attached notice for additional information. Thank you.
>
>
> Olga N. Arroyo
>
> I-405 Sepulveda Pass Improvements Project
> Metro Community Relations - Sunset Segment
>
> Office: 310-846-2357
> Hotline 213-922-3665
>
> Visit us online:
> Facebook: www.facebook.com/405project
> Twitter: www.twitter.com/I_405
> Web: www.metro.net/I-405