The girder installation work on the Skirball Bridge, which has been occurring this week, will now continue for one more additional night.  This work will get extended to Monday night, while tonight's scheduled work will continue as originally planned.  This is a revision of the notice that was sent out on the week of May 23.  Be aware, this work requires the Skirball Bridge to be closed and a full directional freeway closure at night.

 

The remaining work is as follows:

 

  • Friday night, June 3 - Skirball Bridge closure between the hours of 10 pm to 6 am and full northbound freeway closure from the Getty Center Dr ramps to Ventura Blvd. between the hours of 1 am to 5 am.

 

  • Monday night, June 6 – Skirball Bridge closure from 10 pm to 6 am, full southbound freeway closure from Burbank Blvd to the Getty Center Dr ramps from 12 am to 5 am.

 

 

 

Ron Macias

Community Relations Officer

I-405 Sepulveda Pass Improvements Project

(310) 846 - 3564

MaciasR@metro.net

 

I-405 Project Hotline 213-922-3665

www.metro.net/I-405

 