Thursday, June 16, 2011

Sunset Bl bridge area activities

Please see below notices for upcoming work in the Sunset Bl bridge area. Thank you.

 

1.     The contractor will drive steel pile at the NB Sunset Bl on-ramp, using a crane mounted hammer.  This activity is necessary for the reconstruction of the ramp footings.  Day time work is anticipated to start on Monday, June 20, 2011 for approximately two weeks.  Anticipated work hours are from 7am to 7pm, weather permitting.

 

2.    The contractor successfully removed the first half of the existing retaining wall on Sepulveda Bl, between Montana Av and Bronwood Av.  The final phase of retaining wall removal and k-rail placement has been schedule to start on Monday, June 20, 2011. Pedestrian access will be restricted and will be detoured to Church Ln.  Final phase of retaining wall removal between Montana Av and Homedale Av is anticipated to start on Monday, June 20, 2011 for one week.  Wall removal between Homedale Av and Bronwood Av is anticipated to start on Monday, June 27, 2011 for one week.  Work hours are from 8am and 4pm. 

 

3.     As part of the ongoing Sunset Bl bridge reconstruction and the water line replacement, the contractor will be implementing full closures of Sunset Bl between Church Ln and the NB Sunset Bl ramps. Full nightly closures of Sunset Bl are anticipated to start on Monday, June 20, 2011 for one week, followed by intermittent nightly full closures.   Anticipated work hours and full closure times on Sunset Bl are from 10pm to 6am.  Sunset Bl bridge will be open during the day.  WB Sunset Bl traffic will be detoured to Sepulveda Way, to NB Sepulveda Bl, to SB Church Ln, back to Sunset Bl.  EB Sunset Bl traffic will be detoured to NB Church Ln, to SB Sepulveda Bl, to EB Sepulveda Way, back to Sunset Bl.

 

 

 

 

Olga N. Arroyo

 

I-405 Sepulveda Pass Improvements Project

Metro Community Relations - Sunset Segment

 

Office: 310-846-2357