Monday, October 24, 2011

Full Directional Freeway Closure / 4 Nights starting October 25th

ATTENTION RESIDENTS AND BUSINESS IN THE VICINITY OF THE SKIRBALL CENTER DR BRIDGE AND THE I-405 SAN DIEGO FREEWAY

The contractor has scheduled the implementation of a full directional freeway closure for four nights
starting Tuesday, October 25, 2011 during the late night hours, weather permitting. A number of work
activities will be conducted concurrently during these nights of the full directional freeway closures. These
activities are as follows:

 Installation of walkway on the north half of the Skirball Bridge
 Mulholland Bridge column construction work
 Removal and replacement of overhead freeway signs and structures to support freeway widening

Each night, ramps within the freeway closures limits may begin to close as early as 7:00 pm and freeway
lanes will begin to close as early as 10:00 pm, leading up to the full directional freeway closure between the
hours of 12:00 am, midnight, to 5:00 am. See table below for schedule of upcoming freeway closures.

What: The implementation of a full directional freeway closure for several work activities in the area.

When: Work is anticipated to begin Tuesday, October 25, 2011, and last four nights during the late
night hours, weather permitting. See table below for schedule of upcoming freeway closures.

Where: I-405 freeway between the Getty Center Dr. ramps and 101 freeway.

What to expect:
Closure Location Anticipated Night
Southbound I-405 freeway from the 101 freeway to Getty Center Dr.
(freeway lanes closures staring at 10:00 pm)
Oct. 25 & 26

Northbound I-405 freeway from Getty Center Drive to Ventura Blvd.
(freeway lanes closures staring at 10:00 pm)
Oct. 27 & 28

 Sepulveda Blvd. will remain open during the nights of these full directional freeway closures and
will be used as a detour route. Detour maps are available at www.metro.net/405
 Utility relocations will be conducted on the Skirball Bridge during the nights of the full directional
freeway closures which requires the closure of the Skirball Bridge from 10:00 pm to 6:00 am
 Emergency access will be maintained on the bridge at all times.
 Pedestrians will be rerouted to an area outside of the construction zone
 For a listing of daily closures and latest updates visit our website at www.metro.net/405 or follow
us on twitter: twitter.com/I_405 and Facebook at facebook.com/405project