UPDATED 405 Work Activities: Sunset Segment

Please see attached notice for additional information on these and activities.

*Updated Activity Notice*

An additional night for false work installation at the Sunset Bl on-ramp requiring a full street closure of Sepulveda Bl has been scheduled for tonight.

The utility relocation on Sepulveda Bl between Montana Av and Moraga Dr will continue with 24 hours a day-7days a week underground directional drilling for approximately 20 days. This continuous activity is necessary to prevent the excavation from collapsing.

*Revised Notice*

As part of the ongoing utility work on the Sunset Bridge, the contractor will resume the implementation of nightly full closures of Sunset Bl and Church Ln on Wednesday, January 4, 2012 for four weeks, Monday through Friday. Anticipated work hours and full closure times are from 10pm to 6am.