405 Work Notices: Getty Ramps, Sunset, Bellagio Road & Acanto Drive

Please see below notices for additional information on activities in the Sunset Segment. Thank you.

Power relocation work continues on Sepulveda Bl at the Getty ramps.

An additional weekend for vault installation work has been scheduled to start at 9pm Friday, February 24, 2012 through 6am on Monday, February 27, 2012.

Installation of false work for bridge reconstruction at the Sunset Bl has been scheduled from Friday, February 24, 2012 through Wednesday, February 29, 2012 and from Friday, March 2 through Wednesday, March 7, weeknights.

Removal of the freeway wall along NB 405 between Bellagio Rd/Acanto Dr to Getty Center Drive started on Thursday, February 23, 2012 and will continue through Monday, March 19, 2012. Work hours are from 8am to 5pm, weather permitting.