1.      Sepulveda Bl full closure from Ohio Av to Wilshire Bl tonight, May 24, 2013 from 10pm to 10am.

This closure is necessary to safely remove falsework for the northbound I-405 off-ramp to eastbound Wilshire Bl.

2.      Full night closures of Wilshire Bl from Sepulveda to the southbound Wilshire on and off-ramps beginning Friday, May 31, 2013 from 10pm to 5am.

Full night closures of Wilshire Bl from Sepulveda Bl to the southbound Wilshire on and off-ramps are scheduled for Friday, May 31, 2013 through Friday, June 14, 2013 from 10pm to 5am. This closure is necessary to strip the falsework of the northbound I-405 on-ramp from eastbound Wilshire Bl.

3.      Pico Bl pedestrian detour and full night closures of Pico Bl from Cotner Av to Sawtelle Bl, beginning May 24, 2013.

The sidewalk on the south side of Pico Bl at the I-405 overpass will be closed to pedestrians from Friday, May 24, 2013 through Monday, July 15, 2013. The pedestrian access on the north side of Pico Bl has been reconfigured. Westbound Pico Bl has been restriped to two lanes, and the #3 lane will be used for the pedestrian detour route. Pedestrians will be safely protected from traffic and construction with the use of krail. Also, full night closures of Pico Bl from Sawtelle Bl to Cotner Av are scheduled for Tuesday, May 28, 2013 through Friday, June 14, 2013 from 10pm to 5am. During the night closures, pedestrians should use the nighttime pedestrian detour. Please see attached notice for detour routes.

These closures are necessary to complete work on the eastbound I-10 connector to northbound I-405.

4.      REVISION to the Olympic Bl Construction Notice sent May 22, 2013. The full night closures of Olympic Bl scheduled for May 23 through May 29 have been rescheduled. Notice will be sent when new closure dates have been confirmed.

Schedule and details are subject to change. Please see attached construction notices for details.



(click notices to enlarge)

 (click notices to enlarge)
 (click notices to enlarge)


 (click notices to enlarge)

0 comments: