6/24-Erection of Falsework for Northbound Sunset Off-ramp to Commence



Construction Notice Summary: Erection of falsework for the NB 405 Sunset Bl off-ramp will commence on June 24th and will continue until August 2nd, requiring Sepulveda to be reduced to one lane in each direction during off-peak hours from Montana to Church Ln/ Ovada Pl.

·         Erection of falsework for the northbound (NB) 405 Sunset Bl off-ramp will commence on Monday, June 24, 2013.

·         Erection of falsework is expected to continue until Friday, August 2, 2013.

·         Work hours will be 7am to 5pm.

·         This work will require Sepulveda Bl to be reduced to one lane in each direction during off-peak hours.

·         This lane reduction will be from Montana Av to Church Ln/ Ovada Pl.

·         Lane reduction on northbound Sepulveda will be removed by 3pm.

·         Schedule is subject to change based on daily progress and field conditions.

·         Please see attached notice.