Tuesday, July 16, 2013

Construction Notice Update- Sunset Segment



The Sunset segment of the I-405 Project extends from Constitution to the Getty Center Dr ramps. Here is a summary of construction activities starting this week. To minimize email traffic to your inbox, I have included four notices in this message, summarized as follows:

7/15- 8 months: Moraga On-ramp Left Turn Reconfiguration
·         Access to the northbound Moraga Dr on-ramp from northbound Sepulveda has been changed from two lanes to one lane to original configuration for 8 months. Final configuration will re-stripe to two left turn lanes.
o   This configuration will be in place for 8 months.
o   This has been re-striped to the original, pre-construction left-turn lane configuration at this on-ramp.
o   Final lane configuration will be re-striped to two left-turn lanes for added capacity.
o   Northbound on-ramp at Getty Center Dr will be accessible on August 2nd.
o   Skirball Center Dr northbound on-ramp will be accessible during peak hours.
o   Please see attached notice.
7/15-7/26: Retaining Wall Demo and Excavation at Moraga Ramps
·         Construction for a retaining wall located between the Moraga Dr on-ramp and off-ramp will occur from July 15th to July 26th. Activities consist of excavation, demolition of pre-existing wall, and haul-out of debris. Work hours are from 9pm to 6am.
o   Excavation will occur from Monday, July 15th to Saturday, July 20th.
o   Demolition of pre-existing retaining wall will occur from Monday, July 22nd to Wednesday, July 24th.
o   Haul out of demolition debris will occur from Thursday, July 25th to Friday, July 26th.
o   This work will require closure of the Moraga Dr on-ramp and off-ramp.
o   This work will utilize the full Sepulveda closure from Montana to Moraga which has been implemented regularly for 3 months, from 11pm to 6am.
o   Please see attached notice
7/15-8/2: Erection of Falsework at Church Ln Bridge
·         Church Ln bridge deck falsework beams will be set from Monday, July 15 to Friday, August 2nd, from 10pm to 6am.
o   Work activity hours are from 10:00pm to 6:00am
o   Falsework beams will be set for the bridge deck.
o   This work will utilize the full Sepulveda closure from Montana to Moraga Dr. which has been implemented intermittently for three months, from 10pm to 6am.
o   Church Ln will be closed from Sepulveda Bl to 200 ft west of Sepulveda Bl, 10pm to 6am.
o   Please see attached notice.
7/15- 6 months: Storage of Materials at Bellagio Yard
·         A metal storage container with electrical cabinets, poles, and miscellaneous items will be stored at a City-owned parcel located on the west side of Bellagio Rd, 200 ft south of Casiano Rd. for a duration of 6 months.
o   Anticipated duration for storage at this location is 6 months.
o   Materials will be in a metal storage container.
o   Storage will be accessed during the daytime. On a few occasions, it may have to be accessed at night.
o   Storage items consist of electrical cabinets, poles, and other miscellaneous items.
o   Please see attached notice.
***Schedule is subject to change based on daily progress and field conditions.***