7/16-7/30: Drill/Set/Pour Piles for Sound Wall, Cashmere to Montana
·         There will be retaining wall construction west of Sepulveda Bl, from Montana Av to 600ft south of Cashmere St, July 16th to July 30th, 4pm to 12am. Work will consist of drilling, setting, and pouring 91 CIDH piles.
o   There will be retaining wall construction from Tuesday, July 16, 2013 to Tuesday, July 30, 2013 along the west side of Sepulveda Bl, from Montana Av to 600 ft south of Cashmere St.
o   Work hours are from 4pm to 12am.
o   Work will consist of drilling, setting, and pouring 16-in cast-in-drill-hole (CIDH) piles.
o   A total of 91 piles will be set during this timeframe.
o   This work will require closure of lane #2 on southbound Sepulveda Bl, from Montana Av to Constitution Av.
o   Schedule is subject to change based on daily progress and field conditions.
o   Please see attached notice


(click notice to enlarge)

 