Retaining Wall Embankment Work at NB I-405 to EB I-10 Connector



Construction Notice Summary: Retaining wall embankment and slope finishing work on wall along the northbound 405 connector to eastbound 10 will occur from July 15 to July 20, from 9pm to 3:30am. The connector will be closed from 10pm to 5am.

Details:

·         We will be conducting retaining wall embankment and slope finishing work at a retaining wall located along the east side of the northbound I-405 connector to the eastbound I-10 from Monday, July 15, 2013 to Saturday, July 20, 2013.

·         On the street side, the wall runs between National Bl and Sardis Av, along the east side of the connector.

·         Work hours are from 9:00pm to 3:30am

·         Crews will be backfilling along the retaining wall using a backhoe and a ten-wheel truck.

·         Work will require nighttime closure of the northbound 405 connector to the eastbound 10, from 10pm to 5am.

·         Schedule is subject to change based on progress and field conditions

·         Please see attached notice.