Thursday, July 18, 2013

Update: Waterline Relocation at Thurston Circle & Thurston Place



Summary of Notice: Waterline relocation work at the intersection of Thurston Circle and Thurston Pl will occur from Monday, July 22 to Friday, August 30, from 8am to 3pm, Monday through Friday. Flaggers will be present to help direct local traffic

·         Relocation work of a waterline at the intersection of Thurston Circle and Thurston Pl is expected to begin on Monday, July 22, 2013.

·         Work will continue until Friday, August 30, 2013.

·         Work hours are from 8am to 3pm, Monday to Friday.

·         This work requires a lane take on northbound Thurston Circle at Thurston Place.

·         A flagger will be on-site during lane take to help direct traffic.

·         Waterline relocation work will consist of excavation, lay, and backfill activity.

·         Schedule is subject to change based on daily progress and field conditions.

·         Please see attached notice.

(click notice to enlarge)