Friday, August 2, 2013

IMPORTANT Sunset Segment Construction Activity Update



The Sunset Segment of the I-405 Sepulveda Pass Improvements Project runs from Waterford St (just north of Constitution Av) to the Getty Center Dr ramps.

Please note that effective this morning at 6am, the Getty Center Dr on-ramp to the northbound I-405 has re-opened.

8/2-8/10: Northbound 405 Sunset Off-Ramp Demolition Updated

·         The northbound (NB) I-405 Sunset off-ramp will be demolished, 10pm to 6am, from Friday, August 2, 2013 to Saturday, August 10, 2013.
o   The NB I-405 Sunset ON-ramp will be closed August 2nd to August 10th, 10pm to 6am.
o   Sepulveda Bl will be closed from Montana Av to Church Ln:
§  Friday, August 2 and Saturday, August 3, 10pm to 8am.
§  Sunday, August 4, to Saturday, August 10, 10pm to 6am.
o   WB Sunset Daytime Detour: NB I-405 off-ramp to WB Wilshire, to NB Sepulveda, to EB Sepulveda Way, to WB Sunset.
o   WB Sunset Nighttime Detour: NB I-405 off-ramp to WB Wilshire Bl, right on NB San Vicente Bl, right to NB Barrington Av, to Sunset Bl.
o   EB Sunset Detour, Day & Night: NB I-405 off-ramp to EB Wilshire, to NB Veteran Av to EB Sunset Bl.

(click to enlarge notice) 





8/2-8/3: Sunset Bl New Roadway Construction
·         Paving and construction of new roadway and signal and lighting work will occur on Sunset Bl, at the N. Thurston Av intersection.
o   Work will be conducted from Friday, August 2nd to Saturday, August 3rd.
o   Sunset Bl will be closed, from Church Ln to N Thurston Av, 10pm to 7am.
o   Flaggers will maintain local access.
o   Lane #2 on eastbound Sunset will be closed from 7am to 4pm on Saturday, August 3rd, Church Ln to Sepulveda Way.
o   Eastbound (EB) Sunset detour will be EB Sunset to SB Barrington to EB Wilshire Bl to NB Veteran to EB Sunset.
o   WB Sunset detour will be WB Sunset o SB Veteran Av to WB Wilshire Bl to NB Barrington to WB Sunset Bl.

 (click to enlarge notice)




12:00AM, on 8/3: 120-Day Closure of Northbound I-405 Sunset Off-Ramp
·         The northbound (NB) I-405 off-ramp to Sunset Bl will be closed 24 hours a day for demolition and reconstruction, for 120 days, from 12am Saturday, August 3, 2013 to Sunday, December 1, 2013.
o   Daytime detour for westbound (WB) Sunset is the NB I-405 off-ramp to WB Wilshire, right on Sepulveda Bl, right on Sepulveda Way, right onto WB Sunset Bl.
o   Nighttime detour for WB Sunset is the NB I-405 off-ramp to WB Wilshire, right onto San Vicente Bl, right on S Barrington Ave to WB Sunset Bl.
o   Alternate Daytime WB Sunset detour is NB I-405 Moraga Dr off-ramp, right on Sepulveda Bl, right on Church Ln, right onto WB Sunset Bl.
o   Daytime and nighttime detour for eastbound (EB) Sunset Bl is the NB I-405 off-ramp to EB Wilshire Bl, left on Veteran Av, right to EB Sunset Bl.
o   Traffic control officers will be deployed to key intersections to assist with the adjustment of traffic patterns.

  (click to enlarge notice) 


8/2-8/23: Sunset Off-Ramp Abutment & Wall Footing Excavation Updated
·         We will be excavating for an abutment & retaining wall footing for the NB Sunset off-ramp reconstruction, Friday, August 2, 2013 to Friday, August 23, 2013.
o   Work hours are 8pm to 4:30am and 7am to 3:30pm.
o   NB I-405 Sunset ON-ramp will be closed August 2nd to August 23rd, 10pm to 6am.
o   WB Sunset Daytime Detour: NB I-405 off-ramp to WB Wilshire, to NB Sepulveda, to EB Sepulveda Way, to WB Sunset.
o   WB Sunset Nighttime Detour: NB I-405 off-ramp to WB Wilshire Bl, right on NB San Vicente Bl, right to NB Barrington Av, to Sunset Bl.
o   EB Sunset Detour, Day & Night: NB I-405 off-ramp to EB Wilshire, to NB Veteran Av to EB Sunset Bl
o   Sepulveda closed, Montana to Church Ln:
§  10pm to 8am Fri 8/2- Sat 8/3
§  10pm to 6am Sun 8/4- Fri 8/23

 (click to enlarge notice) 



**FOR ALL: Schedule is subject to change based on progress and field conditions***