Wednesday, August 14, 2013

Mulholland Falsework Removal 8.17.13



Update - Mulholland Falsework Removal August 17 and August 24, 2013

The contractor will be removing the falsework on the Mulholland Bridge on Saturday night over the next two weekends.  This will require full directional freeway closures from Valley Vista to Skirball, from 11:00pm until 9:00am.

Saturday, August 17, 2013: Full southbound freeway closure, from Valley Vista to Skirball, from 11:00pm until 9:00am.  Northbound #1, 2, 3 lanes will be closed as a buffer.  Closures start at 11pm and last until 9am.
Saturday, August 24, 2013: Full northbound freeway closure, from Skirball to Valley Vista, from 11:00pm until 9:00am.   Southbound HOV, #1 and 2 lanes will be closed as a buffer.  Closures start at 11pm and last until 9am.

The project has coordinated with the city to ensure that no closures will be taken on Sepulveda Blvd within or around the detour route.


(click notice to enlarge) 
 

0 comments: